Report_Id: 229932 Est NO 0010 |
Date:05/16/2023 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 229932 | Estimate Number | 0010 | Estimate Type | PROGRESS | ||
District Office | PIKEVILLE (12320) Hayes, Vincent | ||||||
Contractor | IRVINE CONTRACTING LIMITED LIABILITY COMPANY | ADDR SN 99 VC Code | |||||
3637 E LAUREL RD | |||||||
LONDON , KY , 40741 | |||||||
Pay Period | 04/23/2023 TO 05/05/2023 | ||||||
Date Approved | 05/09/2023 | ||||||
Primary Proj Number | BR06703932200 | ||||||
Project No. | EMERGENCY | ||||||
Primary County | LETCHER | ||||||
Name of Road | KY 343 | ||||||
Description | REPLACE CULVERT ON KY 343 OVER WRIGHT BRANCH | ||||||
Date Let | 08/01/2022 | Formal Acceptance | |||||
Date Awarded | 08/01/2022 | Date Work Began | 12/06/2022 | ||||
Date Contract Executed | 08/01/2022 | Open To Traffic | |||||
Date NTP Issued | 08/01/2022 | Actual Completion Date | 05/05/2023 | ||||
Current Contract Amount | $1,336,388.53 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $1,336,388.53 |
Total Earnings | $1,256,113.57 |
$1,039,843.58 |
$216,269.99 |
|
Percent Complete | 93.99 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $80,274.96 |
Gross Earnings | $1,256,113.57 |
$1,039,843.58 |
$216,269.99 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $1,256,113.57 |
$1,039,843.58 |
$216,269.99 |
|||
Contract Id | 229932 | Change Order Summary |
County | LETCHER | ||||||
Estimate Nbr | 0010 | Project Number | EMERGENCY | |||||||
Contractor | IRVINE CONTRACTING LIMITED LIABILITY COMPANY | Period | 04/23/2023 TO 05/05/2023 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 229932 | COMMONWEALTH OF KENTUCKY |
County | LETCHER | ||||||
Contract Type | OPCU CULVERT REPLACEMENT | TRANSPORTATION CABINET |
Primary Project Number | BR06703932200 | ||||||
Estimate Nbr | 0010 | Period | 04/23/2023 TO 05/05/2023 | |||||||
Contractor | IRVINE CONTRACTING LIMITED LIABILITY COMPANY | |||||||||
Project | BR06703932200 | Fed/State Project Number | EMERGENCY | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | BR06703932200 | Fed/State Project Number | EMERGENCY | Category | 0001 BRIDGE | |||||||
0005 | DGA BASE | 00001 | TON | 230.00 | 230.000 | 51.150 | 209.500 | 260.650 | 70.00 | 3,580.50 | 18,245.50 | |
0010 | TRAFFIC BOUND BASE | 00020 | TON | 300.00 | 300.000 | 335.320 | 335.320 | 69.00 | 23,137.08 | |||
0015 | CL2 ASPH BASE 0.75D PG64-22 | 00221 | TON | 308.00 | 308.000 | 154.260 | 0.000 | 154.260 | 186.55 | 28,777.20 | 28,777.20 | |
0020 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 132.00 | 132.000 | 209.320 | 0.000 | 209.320 | 228.86 | 47,904.97 | 47,904.97 | |
0025 | DELINEATOR FOR GUARDRAIL BI DIRECTIONAL WHITE | 01987 | EACH | 2.00 | 2.000 | 0.000 | 0.000 | 15.00 | 0.00 | |||
0030 | GRANULAR EMBANKMENT | 02223 | CUYD | 138.00 | 138.000 | 138.000 | 138.000 | 110.00 | 15,180.00 | |||
0035 | EMBANKMENT IN PLACE | 02230 | CUYD | 1,232.00 | 1,232.000 | 726.020 | 1,232.000 | 1,958.020 | 85.00 | 61,711.70 | 166,431.70 | |
0040 | DOUBLE VEHICULAR CHAIN LINK GATE | 02287 | EACH | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 1,000.00 | 1,000.00 | 1,000.00 | |
0045 | GUARDRAIL TERMINAL SECTION NO 1 | 02360 | EACH | 1.00 | 1.000 | 3.000 | 0.000 | 3.000 | 100.00 | 300.00 | 300.00 | |
0050 | GUARDRAIL END TREATMENT TYPE 1 | 02367 | EACH | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 5,000.00 | 5,000.00 | 5,000.00 | |
0055 | CHANNEL LINING CLASS III | 02484 | TON | 473.00 | 473.000 | 235.000 | 238.000 | 473.000 | 70.00 | 16,450.00 | 33,110.00 | |
0060 | CLEARING AND GRUBBING less than one acre approx. | 02545 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 20,000.00 | 20,000.00 | |||
0065 | CONCRETE-CLASS B | 02555 | CUYD | 2.00 | 2.000 | 0.000 | 0.000 | 600.00 | 0.00 | |||
0070 | TEMPORARY SIGNS | 02562 | SQFT | 300.00 | 300.000 | 140.000 | 140.000 | 20.00 | 2,800.00 | |||
0075 | MOBILIZATION | 02568 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 66,000.00 | 66,000.00 | |||
0080 | EDGE KEY | 02585 | LF | 107.00 | 107.000 | 107.000 | 0.000 | 107.000 | 31.23 | 3,341.61 | 3,341.61 | |
0085 | FABRIC-GEOTEXTILE CLASS 1 | 02602 | SQYD | 473.00 | 473.000 | 251.000 | 0.000 | 251.000 | 4.00 | 1,004.00 | 1,004.00 | |
0090 | FABRIC-GEOTEXTILE CLASS 2 | 02603 | SQYD | 366.00 | 366.000 | 0.000 | 0.000 | 4.00 | 0.00 | |||
0095 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 0.050 | 0.950 | 1.000 | 10,000.00 | 500.00 | 10,000.00 | |
0100 | DIVERSIONS (BY-PASS DETOURS) | 02651 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 151,500.00 | 151,500.00 | |||
0105 | STAKING | 02726 | LS | 1.00 | 1.000 | 0.050 | 0.950 | 1.000 | 7,000.00 | 350.00 | 7,000.00 | |
0110 | REMOVE STRUCTURE | 02731 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 25,000.00 | 25,000.00 | |||
0115 | PAVE STRIPING-PERM PAINT-6 IN | 06515 | LF | 748.00 | 748.000 | 3,350.000 | 0.000 | 3,350.000 | 5.00 | 16,750.00 | 16,750.00 | |
0120 | FOUNDATION PREPARATION | 08003 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 150,000.00 | 150,000.00 | |||
0125 | RETAINING WALL | 08018 | SQFT | 1,138.00 | 1,138.000 | 1,200.000 | 1,200.000 | 120.00 | 144,000.00 | |||
0130 | CONCRETE-CLASS A | 08100 | CUYD | 226.50 | 226.500 | 244.500 | 244.500 | 887.00 | 216,871.50 | |||
0135 | STEEL REINFORCEMENT | 08150 | LB | 28,424.00 | 28,424.000 | 28,424.000 | 28,424.000 | 2.50 | 71,060.00 | |||
0140 | S BYPASS PUMPING | 15000 | EACH | 1.00 | 1.000 | 0.000 | 0.000 | 20,000.00 | 0.00 | |||
0145 | S ENCASEMENT CONCRETE | 15012 | LF | 60.00 | 60.000 | 0.000 | 0.000 | 50.00 | 0.00 | |||
0150 | S ENCASEMENT STEEL OPEN CUT RANGE 4 | 15023 | LF | 60.00 | 60.000 | 0.000 | 0.000 | 166.67 | 0.00 | |||
0155 | S FORCE MAIN TIE-IN 08 INCH | 15075 | EACH | 3.00 | 3.000 | 0.000 | 0.000 | 3,000.00 | 0.00 | |||
0160 | S MANHOLE | 15092 | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 11,250.00 | 0.00 | |||
0165 | S MANHOLE ABANDON/REMOVE | 15093 | EACH | 3.00 | 3.000 | 0.000 | 0.000 | 5,000.00 | 0.00 | |||
0170 | S MANHOLE CASTING WATERTIGHT | 15096 | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 1,375.00 | 0.00 | |||
0175 | S PIPE PVC 08 INCH | 15112 | LF | 248.00 | 248.000 | 0.000 | 0.000 | 200.00 | 0.00 | |||
0180 | EROSION CONTROL | 21415ND | LS | 1.00 | 1.000 | 0.650 | 0.350 | 1.000 | 6,000.00 | 3,900.00 | 6,000.00 | |
0185 | G/R STEEL W BEAM-S FACE (7 FT POST) | 21802EN | LF | 112.50 | 112.500 | 241.250 | 0.000 | 241.250 | 100.00 | 24,125.00 | 24,125.00 | |
0190 | CHAIN LINK FENCE * | 24580EC | LF | 45.00 | 45.000 | 45.000 | 0.000 | 45.000 | 35.00 | 1,575.00 | 1,575.00 | |
0195 | ASPHALT MATERIAL FOR TACK NON-TRACKING | 24970EC | TON | 0.63 | 0.630 | 0.000 | 0.000 | 10.00 | 0.00 | |||
Project | BR06703932200 | Fed/State Project Number | EMERGENCY | Category | 0002 DEMOBILIZATION | |||||||
0200 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 21,187.00 | 0.00 | |||
SUBTOT | $216,269.98 |
$1,256,113.56 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |